Today, 7th April, we are processing in import clearing the material from airport and it will be reached at our office tomorrow ( 8th April) before noon.
Therefore please arrange the schedule to send your services person to Bangkok for site work.
- 2 x 1600 kVA transformers are located at the site already(Supalai Lite Sathorn, mid of BKK)
- 1 x 2000 kVA transformer is kept in our warehouse( south of BKK)
Since during 12th – 15th (16th) April period, there is a long public holiday in Thailand (Songkran Festival), the TR rust removing have to settle and already be finished within this week.
Any query or assistance please let us know.