Based on this morning meeting with Valeo I summarize for you as below.
- Mr. Jonas is very reasonable person and understands the issue. He was suggesting options for us, ie, airfreight, sway control commissioning at side, mobile crane for alternative solution.
- Naret has already checked with Wayne regrading delivery time and possible option as below email.
- Mobile crane option will be in consideration by inviting mobile crane company to survey the site and find the proper way to lift the mold. This would be our cost or not but I would think so.
- Airfreight is the also option but would likely not prefer to do due to cost.
- The 1st section of rail installation will be done during Aug 22-25. This area is not a strictly area after the machine arrive, ie, no high work in this area.
- The 2nd section of rail installation will be done during 26-31.
- We need to send time line with all details, ie, option and update schedule to Valeo on Aug 20. Pongpun should summarize this for me and I will send out.
- We have the additional meeting on Aug 21 at 9.00 am at Valeo. I will join the meeting.