Each forecast alternative is evaluated using the risk management process (Section 7.6).
That process evaluates and quantifies the impact of any risk factors inherent to the alternative plan(s).
The quantification includes estimating the contingency required for the remaining work.
Contingency must be forecast like
any other cost account.