Dear Kh.Roungrote
Regarding our conversation for the final work down at 9:00 am on 21 Aug 15(Post pone due to SPX’ somebody was not available) , could you please re arrange the SPX’s representative to attend on time after that SPX shall be signed the Construction Completion Certificate(As per contract article 6.2)
However in case of the operation team has operated since last month and cannot hand over area to do the work which it may impact to carry out the Punch C clear end of Aug’15(Auto Big Bag).
Best Regards,
S.Piyanath