Cooling Water Line : PM had agreed to do back gouging and welding from inside for all the joints of the CW pipe. As of now at site, it was done only for the 2 joints which were utmost bad (3 flange connection joints were back gouged and welded at Laydown B after TJEL QC comment). The welding defects on the rest of the joints were pointed out to PM yesterday 4.30pm. So far no action taken and balance joints were not repaired till now. Now due to the urgency of the line, TJEL welders are repairing ( Back gouging and welding). Please make sure in future PM supervisor or foreman at site follows and completes the comments by TJEL QC at site at the earliest.