Documentation required to plan an internal audit engagement includes information that
A. Resources needed to complete the engagement were considered.
B. Planed engagement work will be completed on a timely basis.
C. Intended engagement observations have been clearly identified.
D. Internal audit activity resources and efficiently and effectively employed.
Answer: (A) is correct.