If the Contractor does not comply with an instruction
within a reasonable period, the Project Manager shall
issue a notice requiring compliance. If within seven
(7) days of receipt of such notice the Contractor does
not comply, the Employer may employ and pay other
persons to carry out any work required by the
instruction. All costs reasonably incurred by the
Employer may be deducted from any monies due or
to become due to the Contractor under this Contract
or shall be recoverable from the Contractor as a debt.