4.Levels and Setting Out of the Works
The Contractor shall, from a bench mark that will be provided by the Employer determine any levels, which may be required for the execution of the Works. The Contractor shall be responsible for the accuracy of this information and for the setting out of the Works and shall entirely at his own costs amend any errors arising from his own inaccurate setting out.