1. Frequency time for testing the doors.
a. 18 - 22 min. depend on each models. But should not over 25 min.
2. 2 door testers can be coverage all door models. If one of them broken the other one can be support.
a. Door tester has some spare devices and manually and BMW provided the training to related persons.
3. Testing found the problem.
a. In the past the user found the problem with the testing. LED on the door doesn't work. They informed BMW and BMW accepted this issue. BMW able to solve by their site.
4. 2 Label Printers. Each door stations connected 1printer.
a. In the past doesn't has any problem with label printers.
5. The 2nd Shift start from 10.30 pm.– 08.30am. the plan for start working on 2nd shift on around March 2016.
6. Host system and D/N printing :
a. Plant A2 (electric) the soft files (PDF) will save to the Jasper folder. Then the user can print out from Jasper with any laser printers.
b. Plant A3 (interior) the DN documents (hard copies) will come out from DN printer and soft files also save to Jasper folder if the hard copies wasn't come out the user can print the soft file form Jasper folder and print out DN by any printers.
c. Zebra printer for DN the user can switch between A2 and A3 in one of them broken.
d. A2 and A3 can support one another in case of some of them broken.
e. 9 Ck3x scanners installed necessary software for their task.
f. Ink and Toner IT dep't will spare the toner to each dep't which working on 2nd shift.