During the second rainy season, the placement of RCC at both the abutments of the dam can continue until reaching the dam crest level. Consolidation grout can be implemented through the low level gallery. In the case of a heavy flood, water will be allowed to overtop the dam section. At the third year of the dry season, the dam construction work at river section can continue together with the concrete placement for spillway and gate installation. All major dam structures are expected to finish within the third year of dry season.