5 CYCLE OF PLAN, DO, CHECK AND ACTION (PDCA)
5.1 PDCA FLOW
1) Plan
2) Do
3) Check and action
5.2 WORK PROGRESS CONTROL BOARD
losses as well as boosts the workers' motivation. The contractor and subcontractors probe the
cause of the difference between the planned and actual progress, which is helpful in
preparing better SOPD