Figure 6: Example illustrating problems when concurrency
(i.e., AND-splits/joins) cannot be expressed directly. In the
example just three activities (B, C, and D) are concurrent.
Imagine the resulting process models when there are 10
concurrent activities (210=1024 states and 10! = 3,628,800
possible execution sequences).