as you know, the BMW is going to start production on Feb-15th both line till to Feb-17th then they're going to have stop for 6 days again during Feb-18th – 23rd for CSR
for Planning side, I'd like to inform you about internal activity in DTS like this;
on Monday Feb-15th
- For Door assembly will start production at 08:30 am. (with no OT) in case you need to prepare line, please do it on this Friday.
o Car production line 1 = 17 cars or 28 min tack time
o Car production line 2 = 10 cars or 48 min tack time
- For JKS please arrange 2 truck stand by at BMW side before 08:00 am. To take BIW from BMW to DTS, for Finished door, will be start to trun back to BMW about 11:30 am. Or 01:00 pm. (depend on DTS door production)
- For QC resident and Co-ordinator BMW,DTS, Forklift driver (Delivery) please start to work at BMW plant at 08:00 am.
- For another division, can start as normal time.
On Tue Feb-16th – Wed-17th till to month end.
- Door production, QC, Logistics and who concerns with Door Assy production please start to work at 08.00 am.
PS: in case you have some problem about VAN service on coming Monday, please consider as appropriate (depend on each department)
And Next is the time for Car production in Mar'16
Please see in "Drak blue" BMW is going to start The Export car (F15) in Day time since Feb-29th, Mar-03rd on ward.
For the Night shift, they didn't update in there plan yet. However, we still keep the time line for Night shift will start in WK11/2016
For the 3rd line (G12) they plan to build start in WK 10/2016