1. Cutter come in __ 26/11
2. Laminate __ 26/11
3. Cut __ 27/11
4. Soft form : R8,R10 (blind edge + soft form) __ 27-28/11
5. Wrap : Front + Drawer __ 30-1/11
6. Cut + Drill __ 1-2/12
7. Edge __ 3/12
Trial sample -internal approval : 4 /12
Final sample -internal approval : 7 /12
Customer approval sample : 10 /12
If U agree or any comment this time plan ,pls let me know your idea.
And request team to prepare Raw material for time plan..
I ask U ,appointment for sample meeting with team on 19/11 10.00-10.30 am
At Intertech room.5 .
Thanks a lot , KV.