-Install the door already but have some defect they will edit tomorow again. and Will install the door conference room and the door Pantry cabinet and laminate sheet magnetic dining wall tomorrow. They will install the aluminum u channel logo wall,dining wall and touch up all for 12/6/15. section top and glass cabinet pantry to install 19/6/15.
-D-NET Install the power outlet and lighting then some and install again tomorrow. Grid suply air and the return air is installed in this week. Part sprinklers, emergency lighting, cctv, access control is being tracking K.best for that day is installed
-KWC Cleaning tomorrow 13:00pm.
-Carpet and vinyl tiles delivery tomorrow and installation 12/6/15.