10.1.2 During the defects liability period, if there are quality problems on equipment and materials, defects of construction technology or unfulfillment of the second party's obligations stipulated in the contract, the first party has the right to get the compensation arising from the damages and economic loss;
10.1.3 At the end of defects liability period, after completing obligations during the defects liability period, the second party should submit the application to the first party to release the abovementioned guarantee for defects liability period