Please let me know what is the problem.
As Khun Pichit told you, we have to improve our internal process.
Please let me know average PR/PO issue duration, and let me know recent duration.
If you take a longer time than previous situation, we must consider another countermeasure.
Please note this delay should directly effect on CITY STEEL construction, it means delay of #2 line SoP.
If we need to postpone #2 line SoP, please let me know as soon as possible.