K. Sukchai informed that during injection machine testing, the machine will run 8 hours a day. In each hour, the machine will use one ton of resin to produce roughly 26,000pcs of 36.08g preforms. On the first testing day, 90% of production should be commercial grade. On second day, 95% should be commercial grade and gradually improve to 97%. However, the preforms should be stored for at least 24 hours before sending to blow.
K. Anuree confirmed that Central planning department preferred the production to start with 36.08g rather than 22.08g
K. Sukchai informed the schedule for Injection machine, and K. Voraphol confirm the building schedule as follows.
Date Description
09-Sep Machine on vessel
15-Sep Injection Building: main construction complete
28-Sep Machine arrive Songkla Port
30-Sep Injection Building: fully complete
02-Oct Machine arrive at PP Plant
09-Oct Machine in place
23-Oct Machine installation complete
26-Oct Start testing injection machine
26-28 Oct: 36.08g testing
29-31 Oct: 22.08g testing
06-Nov Testing Complete
09-Nov Acceptance test
K. Janejira informed lead time of resin is 7 days. She noted the requirement that48 tons of resin should be delivered for the testing (6 days supply, 8 tons a day).
After testing, full production could start for 24 hours a day.
K. Anuree confirmed the resin demand during November and December as follow.
For storage space, K. Seksan and K. Voraphol confirmed that there should not be an issue.
K. Sukchai then informed that resin used for this new injection machine should be fast reheat resin. With fast reheat resin, there are potential of 7-13% saving.
Although, Husky have not yet been notified, there should not be any issue to adjust the machine profile a little bit for fast reheat resin.
------------------
Others issues:
K. Jacky and K. Sukchai will discuss later about Hat Yai injection machine since K. Jacky would like it to have a proper overhaul.
There is possibility of 3 months delay on new line. The building might be ready for Krones machine at the end of March 2016.
Minutes taken by: Jareer
K. Sukchai informed that during injection machine testing, the machine will run 8 hours a day. In each hour, the machine will use one ton of resin to produce roughly 26,000pcs of 36.08g preforms. On the first testing day, 90% of production should be commercial grade. On second day, 95% should be commercial grade and gradually improve to 97%. However, the preforms should be stored for at least 24 hours before sending to blow.K. Anuree confirmed that Central planning department preferred the production to start with 36.08g rather than 22.08gK. Sukchai informed the schedule for Injection machine, and K. Voraphol confirm the building schedule as follows.Date Description09-Sep Machine on vessel15-Sep Injection Building: main construction complete28-Sep Machine arrive Songkla Port30-Sep Injection Building: fully complete02-Oct Machine arrive at PP Plant09-Oct Machine in place23-Oct Machine installation complete26-Oct Start testing injection machine 26-28 Oct: 36.08g testing 29-31 Oct: 22.08g testing06-Nov Testing Complete09-Nov Acceptance test K. Janejira informed lead time of resin is 7 days. She noted the requirement that48 tons of resin should be delivered for the testing (6 days supply, 8 tons a day).After testing, full production could start for 24 hours a day. K. Anuree confirmed the resin demand during November and December as follow. For storage space, K. Seksan and K. Voraphol confirmed that there should not be an issue.K. Sukchai then informed that resin used for this new injection machine should be fast reheat resin. With fast reheat resin, there are potential of 7-13% saving. Although, Husky have not yet been notified, there should not be any issue to adjust the machine profile a little bit for fast reheat resin.------------------Others issues: K. Jacky and K. Sukchai will discuss later about Hat Yai injection machine since K. Jacky would like it to have a proper overhaul. There is possibility of 3 months delay on new line. The building might be ready for Krones machine at the end of March 2016.Minutes taken by: Jareer