3) Identify dependencies between tasks
The work breakdown structure does not show any
dependence among the activities/tasks
How much time does the whole project need if I know the individual
times?
What can be done in parallel?
Are there any critical activities, that can slow down the project
significantly?
Dependencies like these are shown in the dependency graph
Nodes are activities
Lines represent temporal dependencies