Dear Sir,
Final document – Recycle water / Waste water piping system,
Status of final document
Mechanical portion : completed
Control & Instrument portion : completed
Electrical portion : Pending the drawing no. LKBO-ESCO/PPTC-E-1UUUU-E0002 MCC Stater Pump for Recycle water/Waste water piping system (as built)
Civil portion : Pending the drawing no. LKBO-ESCO/PPTC-C-1UUUU-RCW&WSW-ST-C1005 to C1005/21 (as built)
Pending the calculation no. LKBO-ESCO/PPTC-C-CAL-C003 Calculation Sheet for Recycle Water Pit 700 M^3. & Pump House Building (as built)
Pending the calculation no. LKBO-ESCO/PPTC-C-CAL-C008 Calculation sheet for pile capacity (as built)
So, I plan to submit the final document of RCW/WSW system to Owner / OE within Friday 20-05-16.
Please expedite to submit as your document before this Friday krub.