The Employer’s Personnel shall at all reasonable times:
(a) have full access to all parts of the Site and to all places from which natural
Materials are being obtained, and
(b) during production, manufacture and construction (at the Site and elsewhere),
be entitled to examine, inspect, measure and test the materials and
workmanship, and to check the progress of manufacture of Plant and
production and manufacture of Materials.
The Contractor shall give the Employer’s Personnel full opportunity to carry out
these activities, including providing access, facilities, permissions and safety
equipment. No such activity shall relieve the Contractor from any obligation or
responsibility.
The Contractor shall give notice to the Engineer whenever any work is ready and
before it is covered up, put out of sight, or packaged for storage or transport. The
Engineer shall then either carry out the examination, inspection, measurement or
testing without unreasonable delay, or promptly give notice to the Contractor that the
Engineer does not require to do so. If the Contractor fails to give the notice, he shall,
if and when required by the Engineer, uncover the work and thereafter reinstate and
make good, all at the Contractor’s cost