Block I, Transmission Line Construction, the NTP schedule was August 1, 2014. The construction period is 12 Months from August 1, 2014 – July 31, 2015 and the construction should be finished on March 31, 2016. SCOD is April 1,2016.
For Block I the NTP was delay for a month, SSUT should connect the first transmission line in front of SSUT’s Power Plant on August 1, 2015 for energizing. The construction period for the first transmission line is about 6 months.