Regarding our discussed on last mat'l meeting (14 Jan, 2016) about HVPT trial that YMPPD requested us to negotiate with Nitco about mat'l for trial price which higher than CSP price.
The result from our negotiated with Nitco , Mat'l price for HVPT trial will be cheaper than around 50% of quotation that you got in previous.
Because there isn't any charge from Nitco . But still have extra charge of UCC only, special cutting cost Etc.
Therefore, for decision making of HVPT trial depend on supplier consideration which we (UPT & NMT) have been informed to YMPPD on the meeting of regeneration recovery plan in last year 2015 " that if supplier are not assure in quality of products and need to ensure by HVPT trial" .
The any expenses that occur form HVPT , supplier must response by yourself. This is our direction.
But on the other hand, if supplier couldn't response the expenses of HVPT and needn't go on further these items, please inform to us to cancel these items in urgently. We pleased to delete that items accordingly.
Next time , if there are any items that need to trial HVPT or furthermore , please inform us in the period of "Feasibility of Activity" to evaluation total cost of the activity to judgement that items.