The physical meaning of Equation 5.9 is illustrated in Figure 5.9. In this figure, a 5-unit project
is shown with each unit consisting of a simple four-activity network. Three of the four activities
A, B, and C are sequential and each has 5-days duration. The fourth activity D runs parallel to B
and has a duration of 2 days only. Accordingly, A, B, and C are critical activities while activity
D is non-critical with Total Float (TF) of 3 days. As shown in Figure 5.9, the slopes of activities
A, B, and C are the same and are steep up. The slope of activity (D), on the other hand, has been
relaxed by simply starting unit 1 of task D as early as possible while starting the last unit as late
as possible (notice the difference in the CPM networks of the first and the last units). In this
manner, simple analysis of the slope of activity D in the figure leads us to the formulation of
Equation 5.9. Using this approach, the relaxation of non-critical activities can be performed
without violating any logical relationships or crew work continuity requirements.
ความหมายทางกายภาพของสมการ 5.9 จะแสดง ในรูปที่ 5.9 . ในรูปนี้เป็นโครงการ 5-unitแสดงกับแต่ละหน่วยประกอบด้วยง่ายๆสี่กิจกรรมเครือข่าย 3 ใน 4 กิจกรรมA , B และ C เป็นลำดับขั้น และแต่ละคนมี 5-days ระยะเวลา 4 กิจกรรม D วิ่งขนานไปกับบีและมีระยะเวลา 2 วันเท่านั้น ตาม , A , B และ C เป็นกิจกรรมที่สำคัญ ในขณะที่ กิจกรรมD ไม่สําคัญกับลอยทั้งหมด ( TF ) 3 วัน ดังแสดงในรูปที่ 5.9 , ลาดกิจกรรมA , B และ C เป็นแบบเดียวกัน และชันขึ้น ความลาดชันของกิจกรรม ( D ) , บนมืออื่น ๆที่ได้รับผ่อนคลายโดยเพียงแค่เริ่มต้น 1 หน่วยของงาน D ให้เร็วที่สุดเท่าที่เป็นไปได้ในขณะที่เริ่มหน่วยสุดท้ายที่เป็นสายที่สุด ( สังเกตความแตกต่างใน CPM เครือข่ายแรกและหน่วยสุดท้าย ) ในนี้ลักษณะการวิเคราะห์ง่ายของความชันของกิจกรรม D ในรูปที่นำเราไปสู่การพัฒนาสมการ 5.9 . การใช้วิธีการนี้ เพื่อความผ่อนคลายของกิจกรรมสามารถดำเนินการได้ไม่ วิกฤตโดยไม่ละเมิดความสัมพันธ์เชิงตรรกะใด ๆหรือลูกเรือทำงานอย่างต่อเนื่องตามความต้องการ