Container 1 for valve maintenance shall be relocated close to working area and away from laydown area.
2. Valve testing area shall be identified in the layout
3. Would it be possible to extract all the equipment from container and send the empty container to WP-01 (like previous shutdown ) if there is no enough space for SNU container?