It is an opportunity that QC team being involve to review glass together with production engineer as this project is in critical time plan that we must send sample to ARB to review.
This lot of glass will not have all the point in specification but good enough to practice.
We have Go-No Go gauge back from supplier and again the Go-no Go gauge is incorrect that need to fix the pointer on the checking template.
We are conduction SIR to provide feedback to supplier for the point that out of spec that we would like to control. As you are already aware that supplier cannot build glass to specification to drawing, but as long as ARB team review and accepted.
We will give supplier exception on some of the point that out of spec.
To me we are learning and developing glass together with supplier and known an issue of what being accept and not accept