Hello,
Thank you for your time today and for the effort done during the last week!! Congratulations.
I will schedule a call on Friday, to see if you have manage to complete the three points below (or at least the first two) so we can schedule the first mass mailing to the TOP 80-20 suppliers:
I. Classification & Bizz TOP 80-20: to be completed (11 CT & 8 Biz. missing)
II. Email TOP 80-20: to be completed (20 missing)
III. All suppliers in status “Ok Completed”: amend the status of the ones not really completed
I have as well updated in the share folder, the Word document with the minutes/agenda of the meetings we have had and the Excel that shows the plan and the progress. Please, see attached below the Word file (with the review we did today over the job of last week (8) and the actions for this week (9) ) and the updated chart showing the percentage of completion in each phase.