Please clarify commercial conditional as below, I follow PO2040104322 as attachment.
1. Partial delivery& payment is NOT allowed.
2. Delivery Time: 4 weeks ARO (approx. within 12 Nov.15/ PO Plan 15 Oct.15)**
3. Delivery Term: DDP at Job site, Map Ta Phut, Rayong, Thailand
4. Payment condition: 60 days by 100% after delivery at site and Submission of Final Documents (MDR)
5. Delay Penalty: Applied for each shipment with 0.2% per day of total price and 10% limitation.
(Delay Penalty shall be apply on "Date of Equipment on site")
6. Warranty Period: Warrantee Period 12 months after commissioning or 18 months after delivery, whichever comes first.
7. Final Price 12,000.00 THB (exclude VAT7%) bargain 10.44%