Product John requires 2 units of component X and
one unit of component Y to make a finished unit of
John. Component X is produced on a JIT pull system
basis by a separate manufacturing department.
Determine the number of kanbans required for
component X if the lead time is 2 days, the safety
factor is 10%, and the container size is 20 units.