Meeting at STEC
With 1.STEC k.sakulpong 2.TSC k.chumpol 3.SMCC k.peerapong 4.SCN K.kulvadee k.kevalee k.taud NewDraftman 5.TSGNirin
1)Item1 TSG send toSTEC 13/2/15. After customer sign will send color copy (price will deleted) toDOEB
2)Item 2-8. will send toDOEBK.Thitipong ~Monday 16/2/15
3)~18/2/15 DOEB Director K.Thawan will check all document. For drawing approved.
4)~20/2/15.after All Drawing approved. TSC will send letter to DOEB for check CNG using place at STEC
5)~2-4/2/15 DOEB will come to check CNG using place at STEC. with third partySIWA (withSCN,TSG)
6)~6/2/15 SIWA will send PAPER for result of check CNG using place at STEC to DOEB
7)~7-10 STEC will start using CNG