Semple-Brown assemble kitchen tables using bought-in parts of four legs and a top. These have lead times of two and three weeks respectively, and assembly takes a week. The company receive orders for 20 tables to be delivered in week 5 of a planning period and 40 tables in week 7. It has current stocks of 2 complete tables, 40 legs and 22 tops. When should it order parts?