Obligations and Responsibilities of Party (A)
A: Obligations of Party(A)
-Responsible for labor equipment and Topographic Instruments.
-Ensure to have enough money and payment on time as wrote in the contract of road No 5(BOT)
-Ensure to provide all legal document permission of road construction (B.O.T) and main master plan to party (B).
-Ensure to settle the social policy of people land, fence, house and buy land for building (the detour) along the road NO 5 with the local authority and people are not resposible for Party (B).
-Ensure and responsible for settle Mine, and other weapons from the central line of road 50m each sides.
-Ensure and responsible for the consultant firm, engineering, architectures, to inspect the road quality, road's views and other technicals.
-Provide all legal documents related with this construction project which provided by Royal Government of Cambodia.
Strictly cooperate with Party (A) in researching, designing and construction this project following to the technical standard of international civil engineering.
-Provide legal documents such as certificate of confirming the project value, certificate of business registration, patent paper, land title, and other litigation documents, etc.
-Irrevocablely ensure to provide the profit to party (B) in the amounts of ………….% (………………. Percentages).