- Start Painting some part (open ceiling) 7/10/16 they will do it again 10/10/16. K.Suwit Install the walls and plaster some part already. him will work again at 10/10/16. - Lantro Install conduit to completed 8/10/16 and start wiring work 11/10/16 completed 12/10/16. - Intelcralf Conduit on the ceiling at board room completed and the rest including wiring will completed 8-9/10/16. - Dnet Sprinker work start and completed 8/10/16, Air-Con work they will do 7-10/10/16 except office zone. Conduit and wiring for lighting from board room to the storage room completed. Conduit and wiring for smork ditecter completed.