Dear Pahakamon,
One batch need at least two or three days to finish pelletizing . and QC sampled and tested at the first day . so that is why there a date gap .
By the way ,the product process is 1 fill RM per formula , melting ,and blending . QC samples and test . if it is ok , then start pelletizing or making it in to slab .