We have traced the source of the new demand. One of our customers suddenly started buying 0B00 "72 ST 28 TREXA HC" at very large quantities. We have adjusted our forecast accordingly. We predict a demand of approximately 2,000 pcs a month from them. As a result, this week's requirements spiked in order to support the new demand and safety stock quantities.
The other reason for the spike is that I will be out from April 3 - April 18. I am placing my orders ahead of time and combining them. Please advise if the PO ship dates need to be pushed back to account for the larger quantities. These are the PO #'s you should be receiving shortly: