The cost breakdown structure (CBS) in this information system is structured to associate with the level
IV of the WBS or at the work package level. The coding structure of the actual cost code for this information system is also demonstrated in Figure 2. These cost codes are one of the many ways a coding system can be set. The coding system suggested in this information system is found to cover
the scale of works performed by small-to-medium contractors.