1. Item 1.6, please specify inspection report. From monthly claim, you have many items.
2. Item 2.1, Add weekly activities have been done from daily report
3. Item 2.3, No any concerns of construction?
4. Item 2.4: manpower report, put data from attached summary, check it is aligned with daily report.
5. Item 2.5: Equipment, pls summarize data from daily report, there are many items!!!
6. Item 2.6: Schedule update, add Milestone from your MS project, use original plan & actual. Please send MS project file cut-off date 25 Sep15 to us ASAP. We have to attach on our monthly report.
7. Item 3; update RFI from attachment. There are 8 closed, 7 open items.
8. Item 5: VO, please update data. From our last meeting, there was at least one VO approved.