The power intake structures is planned to be located at the left bank around an elevation of +450 m, so the construction site is free from flooding from Nam Theun river. A construction road branching off from the road near dam left abutment is foreseen to facilitate machine mobilization. This road will eventually be upgraded to a permanent road for operation and maintenance purpose.