Within 30 days after signing of contract detailed progress plan is to be worked out by the Builder. An actual progress plan as works are performed shall be given to the Owner every month, thus enabling the Owner to follow the construction progress and identify any critical items at an early. During the outfitting stage, the progress plan shall be worked out every month. Such items of labour or construction where the
Builder intends to use subcontractors shall be followed up with progress plans in the same manner.