“Please note in the supply agreement we have added a provision (new Article 20) relating to our commitment re the performance and reliability guarantee. As expressed yesterday we doubt that there will be sufficient time, in a single site visit, to fully commission the system. The system at VKPC was not totally commissioned nor were the control variables fully set up and tuned during the single visit. Therefore for this project we are saying that unless SKIC commit to a 2nd site visit to allow us to finally commission etc then SKIC can’t not enforce the contractual obligation re performance and reliability guarantee. Please note our position is driven by engineering or technical concerns and not financial considerations and obviously if the system is fully commissioned and controls tuned etc in a single site visit then we would honour the guarantees.”