ข้อ 17 Q42. Which of the following is an appropriate description concerning the activities that are performed in each process of system development?
a) In external design, items on screens and forms are considered.
b) In testing, design documents are reviewed, and system functions are checked in the
documents.
c) In programming, system operation procedures are confirmed by end users.
d) In project execution planning, the internal processing of the system is considered.
ข้อ 18 Q43. Which of the following is an appropriate explanation of reverse engineering?
a) A method for conducting efficient experiments with the fewest possible number of
trials, in consideration for a better combination of multiple factors that should be
confirmed
b) A method for disassembling and analyzing an existing product in order to uncover
its structure and acquire technology
c) A method that transforms work into an ideal form by fundamentally reviewing
workflow and work methods without changing the content of work
d) A method that shortens the time from product development to production, through
the parallel execution of multiple activities that can be performed simultaneously
ข้อ 19 Q46. In project management, it is necessary to manage cost, time, quality, and other factors.
Which of the following is an appropriate description concerning project management?
a) Since cost, time, and quality differ in order of priority according to constraints, a
balance among these must be achieved.
b) Since cost, time, and quality are all independent of each other, there is no need to
achieve a balance among these.
c) Since cost and quality are in direct proportion to each other, management can be
performed with the focus on either one of these.
d) Since cost and time are in inverse proportion to each other, management can be
performed with the focus on either one of these.
ข้อ 20 Q47. Which of the following is an appropriate activity that is performed in “project scope
management” defined in the PMBOK (Project Management Body of Knowledge)
Guide?
a) Organizing a project team and developing staff members
b) Defining all activities required for a project without any omissions
c) Identifying the stakeholders of a project and deciding the communication method
d) Identifying the project risks and considering appropriate action plans