Dear Khun Kornkot,
We understand your concern and I will be in the meeting as per your request. We also would like to confirm our handover plan as our internal discussion with Khun Danai our PM as following;
1. Week 10-16 July
Up to yesterday(11/07/16) we have handover to hotel for 40 rooms.
On 14/07 : we plan to hand over all room in floor 28 : 16 rooms
On 15/07 : we plan to hand over all room in floor 27 : 10 rooms
By the end of the week there will be 66 rooms handovered to hotel. The balance will be 36 rooms.
2.Week 17-23 July
On 19/07 : we plan to handover all room in floor 31
On 20/07 : we plan to handover all room in floor 32
On 22/07 : we plan to handover 3 rooms in floor 33
By the end of the week there will be 81 rooms handovered to hotel.
3.Week 24-30 July
On 25/07 : we plan to handover all room in floor 33,34
On 30/07 : we plan to handover all room in floor 35,36
By the end of this week all room will be handovered to hotel total 102 rooms.
You may concern on the long duration for handover of first 2 floors has taken quite sometime and worry how can we expedite it with 3 remaining weeks as above plan. We have learned our problem on this first 4 floors and avoid on repeating those defection on the floor above L.30th.
We can see the result on floor 31 which we request for M2 inspection can turn to be Handover status right away. We believe that there will be more rooms can turn to Handover status during the M2 inspection for level 31-32 within this week.
For the executive lounge completion,we are working on the schedule with our dub contractor closely. There is some financial difficulty that we need to support our sub contractor. We will resolve it urgently and submit you the plan within Friday 15/07.
Best regards,
Sirilak L.