If the Supplier fails to remedy the defect or damage by this notified date and this remedial work was to be executed at the cost of the Supplier under Sub Clause 11.2 (Cost of Remedying Defects), the Owner may (at his option and irrespective of the nature or gravity of the defects or the repair costs):