Dear K. Damkerng
Could you please help to check whether it is break-case item lists to be agreed by internal team. If not , please share and use this email loops to work as break-case collaborate team project due to it is quite delay from our discussion.
Break-case project of 3M timeline is set as tentative follows:
1. SCM development by K. Damkerng - confirm break-case items - within 09 October 2015
2. Change parameter process by commercial within 13 October 2015
3. IM process within 15 October 2015
4. Inform to DC within 16 October 2015
5.1st delivery should be within 23 October 2015
If anyone in this loop have any concerns (both 3M and BIGC team)., don't hesitate to let me for ensuring that we have the availability products to be sell and received the right income of BIGC supercenter