1. To reach project objective (20 year), there’s very slim chance to expand the current one.
2. It is better to have two plants (meaning that to keep the existing one). In case one is shut down, PCSD still have a stand by.
3. It is predictable that the size of the population and industry will be increasing, though not that sharp, it’s wise to prevent the problem in advance.
Assume that you are one of the stakeholders, discuss and answer the following questions:
1. List 5-7 people of major stakeholders in this case?
2. Identify Risk and its consequence of this project if the construction of the new plant option is chosen.
3. Provide risk assessment and risk response for each risk identification.