For example, the project manager might estimate
that a file-conversion activity could be completed in as
few as twenty days or could take as many as thirty-four
days, but is most likely to require twenty-four days.
Using the formula, the expected activity duration is 25
days from the calculation:
(20 + 4 x 24 + 34) / 6 = 25