cannot perform preventive maintenance after corrective maintenance
and therefore the teams have to be allocated to either
corrective or preventive maintenance tasks, if ‘Corrective maintenance
or preventive maintenance’ option is considered in the
simulations. If ‘Preventive maintenance after corrective maintenance’
option is considered, the O&M technicians can perform
preventive maintenance after corrective maintenance is completed,
so the teams are responsible for any kind of maintenance
tasks. If ‘Preventive maintenance only after corrective maintenance’
option is considered, the preventive maintenance can only
be done after corrective maintenance is completed, so the teams
cannot be allocated for only performing preventive maintenance.
These three alternatives provide a detailed understanding about
what order the preventive maintenance needs to be performed for
increased power production.