Today progress for pile driving work.
Rig No.1 continue work at GIS area and finished for 8 Nos.
Note: Pile No. 3740 tip pile broken.
Rig No.2 continue work at GAS compressor area and finished for 7 Nos.
Ring No. 3 continue work at Power block area-1 and finished for 5 Nos.
Note: Pile No. 3027 tip pile broken.
Ring No. 4 Finished for inspection by inspector and plan to start pile drive at Central control building area please coordinate with TTCL for start pile within tomorrow.
Please request to TTCL for inspection pile material delivery to site.