Dear Tonchai
BU Mr. Yang reply for UL status:
1. At present, as TTL plant is ready to provide sample and test equipment for the UL factory inspection ( the required factory inspection information and sample size & amount has been provided said by Mr. yang), then we can notice UL to arrange TTL factory audits, UL will send staff to inspect after notice 1 to 2 weeks.
2. After UL testing & inspection samples, TTL can obtained the initial eligibility, and can start a small amount of production, UL will sampling and testing of the production line again, up to UL laboratory schedule, after TTL send test there will need about a month and the report will come out for Taiwan BU experience.
3. Production inspection sampling and testing of sample OK, then it is incomplete qualify of UL, up to UL laboratory schedule, it was about a month after sending test sample, then the report will come out for Taiwan BU experience.
From the above information, it will take more than 1 month to make the UL certification.
Above, I have translate from the content of BU Mr. Yang.