Obtaining this clearance is prerequisite for EXCAVATION PERMIT.
2. This clearance shall be obtained for a maximum period of 15 days, except at construction
sites, non-operational areas, where it shall be for a maximum period of 1 month.
3. This clearance shall be kept attached with Excavation permit at site.
4. The clearance shall be issued in triplicate, original (pink) for permittee, first copy (white)
for issuer and second copy (yellow) for Fire station. The clearance shall be initiated by
executer.
5. On issue, original copy will be with executor, duplicate copy with Fire Station and
triplicate copy with area in-charge / GSI (Gas Safety Inspector).
6. The clearance by area in-charge/ GSI shall be given just before clearance by shift FSO
and registration at Fire Station. At last shift FSO will also check that clearances from all
other dept. have been received.
7. This clearance shall be considered issued after registration at Fire Station.
8. When job is completed, the receiver shall collect all the copies, and enclose them with
closed copy of Excavation Permit before handing over to permit issuer. Permit issuer in
turn after closing the permit will return the same to Fire Station.